Sindh Chief Minister Murad Ali Shah on Thursday removed the head of the Sindh Building Control Authority (SBCA) and ordered the suspension of 16 of its officers after a building collapse in Karachi’s Baloch Colony killed three people. The Karachi building collapse has also cost the East deputy commissioner and a senior police officer their posts, and the chief minister has ordered the arrest of the building’s owner and builder.
Waseem Shamshad, who served as both Sindh local government secretary and SBCA director general, was removed from both posts on the chief minister’s orders. His services have been surrendered to the federal government, and the chief minister has asked the federal government to suspend him and order a formal inquiry into his role.
The chief minister took the decisions while chairing a high-level meeting at CM House on Thursday, a day after the six-storey under-construction building came down in the Administrative Society area near Baloch Colony.
Three senior officials removed over negligence
The chief minister also ordered the removal of East Deputy Commissioner Nasrullah Abbasi and Senior Superintendent of Police (SSP) East Zubair Sheikh over alleged negligence. The decision on the police officer was taken on the advice of Home Minister Ziaul Hasan Lanjar.
“I will not tolerate any incident that results in the loss of human life or causes suffering to people,” the chief minister said at the meeting, according to The Express Tribune.
The chief minister directed the police to arrest the building’s owner, Salman Tahir, and the builder, Zeeshan, at once. He also told the chief secretary to include the building’s architect and structural engineer in the investigation, so the inquiry can establish whether the construction followed the approved plan and building regulations.
He further directed that a comprehensive and transparent probe be carried out and that strict action be taken against any other SBCA employee found responsible. Public safety must remain the foremost responsibility of every government department, he said.
Sixteen SBCA officers suspended
Along with the removals, the chief minister ordered the suspension of 16 SBCA officers and an inquiry against them. He warned that any SBCA employee found involved in negligence or misconduct would face strict disciplinary action.
Police have detained five people, including the contractor, for questioning. The authority has also sealed 12 other under-construction buildings in the neighbourhood and started checking their records and approvals.
A team from the chief minister’s inspection unit has visited the site. Led by member Anwar Sher, the team collected samples of steel bars and other construction material from the rubble for testing.
Approved for three floors, built to seven
The building stood on a 600-square-yard plot and had been approved in March 2026 for a basement, a ground floor and one additional storey. Six extra floors were then added, turning it into a residential complex of more than 20 flats. Work on a seventh floor, planned as a penthouse, was under way when the structure collapsed on Wednesday.
Around 30 labourers were inside the building when it gave way. Three people were killed and 14 were injured. Rescue teams pulled the injured from the rubble and recovered three bodies.
A local resident told The Express Tribune that work on the seventh floor had begun on Tuesday, and that boring work for underground water had caused strong ground vibrations in the area.
Search operation continues at the site
The search operation continued at the site on Thursday. Rescue 1122 said families of 17 people had reported them missing, though officials have not confirmed the number.
Rescuers razed a wall of a vacant plot next to the site to create an entry route, and heavy machinery was brought in to clear the rubble. A Rescue 1122 team has also entered the collapsed structure to look for anyone still trapped.
What the Karachi building collapse reveals
This is not the first time a building has come down in Karachi over illegal extra floors. Feature Pakistan has reported on earlier collapses in the city, including a building collapse on Manghopir Road and a construction pit incident in Nazimabad.
The pattern is familiar. A builder gets approval for a small structure, adds floor after floor without permission, and the authority meant to stop it looks the other way. The SBCA exists to check plans, inspect sites and seal illegal work. When 16 of its officers face suspension over one building, the failure is not limited to a single file.
The 12 sealed buildings in the same neighbourhood will show whether the authority checks approvals before the next collapse, rather than after it. For the families of the three dead workers and the 17 reported missing, the inquiry must answer a simple question: who allowed a three-floor approval to become a seven-storey building?
Frequently asked questions
Who was removed after the Karachi building collapse?
Sindh Chief Minister Murad Ali Shah removed local government secretary and SBCA director general Waseem Shamshad from both posts. He also removed East Deputy Commissioner Nasrullah Abbasi and SSP East Zubair Sheikh, and ordered the suspension of 16 SBCA officers.
How many people died in the Baloch Colony building collapse?
Three people were killed and 14 were injured when the six-storey under-construction building collapsed in the Administrative Society area near Baloch Colony on November 25. Families of 17 people have reported them missing, though officials have not confirmed the number.
Why did the building collapse?
The building had been approved in March 2026 for a basement, a ground floor and one additional storey, but six extra floors were added. Work on a seventh floor was under way when it collapsed. An inquiry will establish whether the construction followed the approved plan and safety standards.
Who has been ordered arrested?
The chief minister directed the police to arrest the building’s owner, Salman Tahir, and the builder, Zeeshan, at once. Police have already detained five people, including the contractor, for questioning.
What happens next in the case?