Pakistan Invites Turkmenistan to Join CASA-1000
Pakistan has invited Turkmenistan to join the CASA-1000 power project, extending a Central Asian electricity link that already connects Tajikistan and Kyrgyzstan to Afghanistan and Pakistan. The invitation was made at a meeting in Islamabad on Monday between Federal Minister for Power Sardar Awais Ahmad Khan Leghari and his Turkmen counterpart, Annageldi Saparov.
The CASA-1000 project is designed to carry up to 1,300 megawatts of electricity, mainly in the summer months. Of that total, 300MW will go to Afghanistan and 1,000MW will come to Pakistan. Pakistan has also backed Tajikistan and Kyrgyzstan in exploring an extension of the transmission line to Uzbekistan and Turkmenistan.
The two ministers held detailed talks on energy cooperation and regional grid connectivity. The Turkmenistan-Afghanistan-Pakistan, or TAP, power transmission project was a key focus of the meeting.
What CASA-1000 is and why it matters
CASA-1000 links the hydropower surpluses of Tajikistan and Kyrgyzstan with the electricity deficits of Afghanistan and Pakistan. Pakistan, Tajikistan, Afghanistan and Kyrgyzstan are the key partners in the project, and the transmission line passes through Afghanistan.
Tajikistan has already built a transmission line for electricity imports by Afghanistan, and CASA-1000 will supply additional power to Kabul. According to the World Bank’s January 2026 update, infrastructure work in Pakistan, Kyrgyzstan and Tajikistan has largely been completed, while Afghanistan remains the critical missing link, where construction resumed in December 2024.
The project matters because summer demand keeps rising. Leghari said future industrial and commercial activity in Gwadar would spark an extraordinary surge in electricity demand. Pakistan’s power generation is currently in surplus, and the government is introducing a competitive energy market. Leghari said converting CASA-1000 from a one-way flow into a two-way flow would let partners exchange power in times of need and make the project more sustainable.
The TAP project and Gwadar
Leghari told the meeting that Pakistan had encouraged Tajikistan and Kyrgyzstan to explore extending the CASA-1000 line to Uzbekistan and Turkmenistan. He proposed that Iran and Turkmenistan could evaluate enhancing the electricity transmission capacity for Gwadar through the Iranian grid, with a joint group of experts examining the proposal.
On the TAP project, Leghari said seven fundamental technical datasets were required. Pakistan has provided three, but the exchange of technical information from Turkmenistan needs to be expedited. He proposed a meeting of technical working groups to draw up a clear roadmap within a few weeks.
Saparov reiterated his country’s resolve to complete the TAP project, which he said would provide electricity to more than 300 million people in the region. Turkmenistan has already completed the transmission line up to Afghanistan. The remaining phases and feasibility assessment of the 1,150-kilometre, 500-kilovolt, 1,200MW project from Afghanistan to Quetta will go through the technical working group. Saparov assured that Turkmenistan would share the required data soon and that he would personally oversee the project’s matters. Both sides agreed to maintain regular contact between focal persons to resolve technical issues and complete the feasibility study.
Energy ties and the wider picture
Leghari said Pakistan was committed to integrating regional energy markets and providing affordable electricity. He stressed that economic and financial viability was essential for projects like TAP and CASA-1000, adding that this approach ensures end-consumers get the direct benefit.
The energy talks sit alongside a wider push to deepen ties with Central Asia. Pakistan has been working to secure cheaper energy supplies, including a revised LNG deal with Qatar, while Leghari has warned power distribution companies to step up detection of electricity theft, as reported in October.
The fiscal backdrop matters too. The State Bank’s annual report projects growth of 3.5 to 4.5 per cent this fiscal year, and cheaper imported power would help keep industry competitive. The COP31 draft deal also calls for a faster shift away from fossil fuels.
Trade also featured in the visit. Federation of Pakistan Chambers of Commerce and Industry President Atif Ikram Sheikh and Turkmenistan Chamber of Commerce Chairman Gurdov Mergen Meretdurdyevich agreed to strengthen bilateral trade and investment ties.
What happens next
The technical working groups of Pakistan and Turkmenistan will now meet to work out a roadmap for the TAP project within a few weeks, and Turkmenistan is expected to share its remaining technical datasets.
For CASA-1000, the test remains Afghanistan. Construction there resumed in December 2024, but the line cannot carry power to Pakistan until the Afghan section is complete. If Turkmenistan joins, the project would gain a second major supplier, but only if the security and financing of the Afghan stretch hold.
Frequently asked questions
What is CASA-1000?
CASA-1000 is a power transmission project that carries up to 1,300MW of electricity from Tajikistan and Kyrgyzstan to Afghanistan and Pakistan, mainly in the summer months.
How much electricity will Pakistan get from CASA-1000?
Pakistan will receive 1,000MW, while Afghanistan will receive 300MW.
Why has Pakistan invited Turkmenistan to join?
Pakistan wants to extend the transmission line to Turkmenistan and Uzbekistan, widen the supplier base, and meet rising demand, including the expected surge in Gwadar as industry and commerce grow there.
What is the TAP project?
The Turkmenistan-Afghanistan-Pakistan power transmission project will carry electricity from Turkmenistan through Afghanistan to Quetta, over a 1,150-kilometre, 500-kilovolt line with 1,200MW capacity.
What is holding CASA-1000 back?
Afghanistan is the critical missing link. Infrastructure in Pakistan, Kyrgyzstan and Tajikistan is largely complete, but construction in Afghanistan only resumed in December 2024.