Islamabad Expressway Service Road to Be Done in 60 Days

Islamabad Expressway Service Road to Be Done in 60 Days

The Islamabad Expressway service road will be completed within 60 days, Interior Minister Mohsin Naqvi said on Tuesday after a visit to the project site.

Naqvi reviewed construction progress during the visit and said the project had been held back by a gas pipeline that crossed the route. He said the authorities had now resolved all related issues, which cleared the way for work to move ahead at full pace.

Officials briefed the minister that 40 per cent of the project had been completed. They assured him that the remaining work would finish within the set time. The 60 day deadline points to completion by the middle of January 2027.

Why the project had stalled

The service road runs beside the main Islamabad Expressway, one of the busiest routes in the capital. It carries local traffic for the housing sectors and commercial areas along the expressway, and it takes pressure off the main carriageway.

A gas pipeline had stood in the way of construction. Naqvi said the pipeline issue had now been settled. He did not give details of the settlement, but he said no obstacle remained that could delay the work further.

The minister said the government was also developing the Islamabad Expressway to motorway standards. The aim is to cut travel time between Islamabad and Rawalpindi, two cities whose daily traffic flows into each other every morning and evening.

What the Islamabad Expressway service road means for commuters

Naqvi said the service road would benefit a large population living and working along the expressway. He added that the authorities were considering extending it beyond Koral.

The announcement matters because the expressway has been under pressure for years. New housing schemes have added thousands of vehicles to the route, and the service road has stayed incomplete while that traffic kept growing.

Feature Pakistan has followed the expressway works closely. In November, 124 structures were demolished along the Islamabad Expressway as part of the wider effort to clear the route, and the Kashmir Chowk underpass was promised to open within days. The service road deadline is the latest step in the same programme of work on the capital’s main north-south route.

The National Highway Authority is also moving ahead with wider road plans. It has advanced four public-private partnership projects, including the M-10 and the Guru Nanak Expressway, which shows that the expressway works sit inside a larger national push to rebuild major roads.

Green cover on the rise

Naqvi also spoke about the capital’s green cover during the visit. He cited a report from the Space and Upper Atmosphere Research Commission, SUPARCO, which found a 28 per cent increase in Islamabad’s tree cover over the past 18 months.

He said the authorities were planting more trees in areas with limited greenery and working to expand the capital’s green spaces. The tree cover figure gives the road project a second measure to watch, since new road works in the capital often come with questions about the trees they displace.

The minister’s visit fits a pattern of close attention to Islamabad’s civic works. The Capital Development Authority has been carrying out a facelift of markets across the city, and Islamabad has also launched QR code payment for traffic fines. The service road is the largest of these works, and its 60 day deadline is now the test of whether the promises will hold.

For commuters, the proof will be simple. If the road opens in January, the daily run between Islamabad and Rawalpindi should ease. If it slips, the same traffic will keep squeezing onto the main carriageway.

Frequently asked questions

When will the Islamabad Expressway service road be completed?

The service road is due to be completed within 60 days of the announcement on 17 November 2026, which points to the middle of January 2027.

How much of the project is complete?

Officials told Interior Minister Mohsin Naqvi that 40 per cent of the project had been completed when he visited the site.

What had delayed the service road?

A gas pipeline had hindered construction. The minister said the authorities had now resolved all issues linked to the pipeline.

Will the service road be extended?

The authorities are considering extending the service road beyond Koral, though no final decision or date has been announced.

What did the minister say about Islamabad's trees?

He cited a SUPARCO report showing a 28 per cent increase in Islamabad’s tree cover over the past 18 months, and said more trees were being planted in areas with limited greenery.

Feature Pakistan News Desk
Feature Pakistan News Desk
Feature Pakistan News Desk is the editorial team of Feature Pakistan, an independent digital news platform based in Pakistan. The desk reports national, world, business, sports, technology, health and education news, and every story is cross-checked against multiple sources before it is published. To reach the newsroom — including for corrections — email featurepakistanofficial@gmail.com or use the Contact page at featurepakistan.com/contact-us/.

opinion