Rs3bn AFIC Underpass Planned for Rawalpindi’s The Mall

Rs3bn AFIC Underpass Planned for Rawalpindi’s The Mall

The Punjab Highway Department has prepared a PC-I and design for the AFIC underpass in front of the Armed Forces Institute of Cardiology on The Mall in Rawalpindi, at an estimated cost of Rs3 billion. The project is now awaiting formal approval from the Punjab government.

A senior district administration official told Dawn that the department had completed the necessary paperwork and could begin construction once the provincial government approves the project. Dawn reported that the underpass will form part of the Punjab government’s plan to create a signal-free corridor between Koral Chowk and Motorway Chowk.

The AFIC underpass plan

The proposed underpass will sit at Station Mor, the busy point outside AFIC and the Military Hospital, where traffic from The Mall, Peshawar Road and the hospital meets. The National Engineering Services Pakistan has recommended the project as part of the wider plan to keep traffic moving along the corridor.

The official said the AFIC underpass could be completed within two to three months if the provincial government gives the go-ahead next month. The Punjab Highway Department plans to begin work soon after the completion of the Race Course Park and Charing Cross underpasses.

The wider corridor

The underpass is one piece of a 25-kilometre signal-free corridor from Koral Chowk to Motorway Chowk. The government aims to cut travel time between Islamabad Expressway and Motorway Chowk to 15 to 20 minutes.

Three government departments are working on different sections of the corridor. The National Highway Authority is rehabilitating the road between Motorway Chowk and Chur Chowk, while the Punjab Highway Department is handling the underpasses at Race Course Park, Charing Cross and AFIC. The Rawalpindi Development Authority plans to rehabilitate Old Airport Road between Koral Chowk and Ammar Chowk.

With the completion of the ongoing and planned work, the signal-free corridor would be ready by June 2027.

Work already done

Much of the corridor is already taking shape. The GPO underpass was completed last year, and the Kutchery Chowk remodelling finished in May.

The two underpasses on Peshawar Road at Race Course Park and Charing Cross are 75 per cent complete and are expected to be finished by the end of December. The Race Course underpass will have two lanes for northbound traffic, along with three-level road lanes to ease traffic movement and turning. The Charing Cross underpass is being built to accommodate southbound traffic, with two underpass lanes alongside two-level road lanes.

Work is also under way to rehabilitate and expand the road from Bungalow No. 276 to Raffay Mall on Peshawar Road, with utility services shifted underground to keep traffic moving.

The Rawalpindi Development Authority will soon launch the Old Airport Road rehabilitation project, rebuilding the road, improving utility lines and rebuilding joint pickets.

What happens next

Once the Punjab government approves the AFIC underpass, work is likely to start soon after the Race Course and Charing Cross underpasses finish in December. The project was not built alongside the GPO underpass because diverting all traffic through Haider Road via Station Mor would have created extra traffic management problems.

An underpass at Ammar Chowk is also planned, but only after the Old Airport Road and AFIC work is complete. Beautification and green belts will follow the Kutchery Chowk and GPO pattern, giving the stretch a uniform look reflecting Potohar culture.

The project matters for Rawalpindi’s daily life. The city has seen steady work on its roads and public buildings, from the survey of 143 dangerous school buildings now under way to the pressures on household budgets tracked in Rawalpindi’s food prices. The city has also dealt with unusual cases, including nine lions found at a Rawalpindi home. Infrastructure on this scale, such as the Rs16.7bn Islamabad cricket stadium nearby, shows how much public money is flowing into the region’s roads and venues.

Frequently asked questions

Where will the AFIC underpass be built?

On The Mall in Rawalpindi, in front of the Armed Forces Institute of Cardiology and the Military Hospital, at the busy Station Mor junction.

How much will it cost?

The Punjab Highway Department has estimated the project cost at Rs3 billion. The design and PC-I are ready, and the project awaits approval from the Punjab government.

When will construction start?

Work could start after the Race Course Park and Charing Cross underpasses finish in December, if approval comes next month. Construction would take two to three months.

What is the signal-free corridor?

It is a 25-kilometre route from Koral Chowk to Motorway Chowk that the Punjab government wants to make free of traffic signals, cutting the Islamabad Expressway to Motorway Chowk journey to 15 to 20 minutes. The corridor is expected to be ready by June 2027.

Why was the AFIC underpass not built with the GPO underpass?

Building it at the same time would have forced all traffic through Haider Road via Station Mor, creating extra traffic management problems.

Feature Pakistan News Desk
Feature Pakistan News Desk
Feature Pakistan News Desk is the editorial team of Feature Pakistan, an independent digital news platform based in Pakistan. The desk reports national, world, business, sports, technology, health and education news, and every story is cross-checked against multiple sources before it is published. To reach the newsroom — including for corrections — email featurepakistanofficial@gmail.com or use the Contact page at featurepakistan.com/contact-us/.