Pakistan Railways Maintenance Probe: 43 Locomotives Hit
A Pakistan Railways maintenance probe is under way into poor upkeep of locomotives and wagons, shortages of spare parts and the closure of workshops, Railways Minister Hanif Abbasi said on Monday.
Dawn reported that the minister spoke at a ceremony after opening a rebuilt railway bridge on the Lahore-Faisalabad track, which floods had damaged in July.
“A probe is currently underway regarding poor maintenance of the passenger coaches, freight wagons and locomotives, closure of the railway workshops and shortage of spare parts,” Abbasi said. “Some wagons were operated in substandard condition because essential components were missing.”
Lahore-Faisalabad bridge rebuilt in 45 days
The bridge was rebuilt in 45 days, 15 days ahead of its 60-day deadline. Abbasi credited the hard work of railway employees and effective management.
Around 1,500 feet of track was washed away by floods on July 27. Restoration began on Sept 23 and finished within 45 days.
Trains have resumed on the track: the Shalimar Express, Karakoram Express, Badar Express, Ghouri Express and Ravi Express, along with freight train 503.
Pakistan Railways maintenance probe widens to workshops
The probe covers more than rolling stock. A technical assessment of passenger coaches has been completed to find and fix defects. Similar assessments will now cover freight trains, rolling stock and railway tracks.
The CDL workshop has been closed for 15 years, its wheel machine dead since 2007-08. The facility once made 253 items, but production has almost stopped.
The government is working to restart local manufacturing of essential railway parts to cut dependence on imports. Production of safety brackets and other needed parts has already begun.
Modern facilities have been introduced at stations in Rawalpindi, Khanewal, Lahore and Kotri. Projects for Taxila, Rawalpindi and other stations are under way or at the tendering stage.
43 locomotives to run at full power by Dec 15
Abbasi said 43 GEU-43 locomotives were running on only two or three traction motors instead of six, cutting their capacity to haul 3,400 tonnes.
The department has decided to restore all 43 locomotives to full operational capacity by Dec 15.
The railways now runs nine trains daily, rising to 14 between Jan 10 and 20.
The probe and the repair plan sit alongside a wider push to fix the railway’s finances and operations. The government has deferred the ML-3 rail project for a third time, while the Karakoram Express has gone private on the Karachi-Lahore route. Pakistan Railways has also introduced a digital ticket refund system for passengers.
ML-1 work moves ahead with ADB and local banks
Abbasi said the ML-1 upgrade was moving ahead with support from the Asian Development Bank and a consortium of local banks. Agreements for the Rohri-Karachi section are expected in December or January.
Funding for the roughly 449km Rohri-Multan section is being arranged through local banks. The historic Rohri Junction, around 150 years old, will reopen after its upgrade on Jan 15, with modern escalators, CIP lounges and five-star-standard accommodation for drivers and guards.
Safety, digitalisation and staff health
On level-crossing safety, Abbasi said Punjab Chief Minister Maryam Nawaz had assured Rs3bn for railways next week. The full project carries about Rs9.7bn, with the first phase due by March 30. Rs5bn this year and Rs5bn next year are set aside to cut crossing accidents, and Punjab has also assured Rs5bn to upgrade eight branch routes for diesel multiple unit (DMU) trains.
Digitalisation will finish by Dec 31, allowing real-time monitoring of trains and derailment alerts. Hepatitis screening will cover around 60,000 employees and 3,500 railway police, with free treatment for those diagnosed. The railways has also set a first-ever target of selling scrap worth about Rs10bn this year.
The safety push follows recent accidents. The Jaffar Express derailed near Rawalpindi station, and a derailment at Garhi Shahu disrupted Lahore rail traffic.
Frequently asked questions
What is the Pakistan Railways maintenance probe about?
It covers poor maintenance of coaches, wagons and locomotives, spare-parts shortages and closed workshops.
How many locomotives are affected?
43 GEU-43 locomotives run on two or three traction motors instead of six. All will be restored to full capacity by Dec 15.
What happened to the Lahore-Faisalabad bridge?
Floods washed away 1,500 feet of track on July 27. The bridge was rebuilt in 45 days and trains resumed.
What is happening with ML-1?
Rohri-Karachi agreements are expected in December or January. Funding for the 449km Rohri-Multan section is being arranged through local banks, and Rohri Junction reopens on Jan 15.
What safety work is planned at level crossings?
Punjab will give Rs3bn next week towards a Rs9.7bn project, first phase due by March 30. Rs5bn this year and Rs5bn next year are set aside to cut accidents.