Reko Diq Project Cost Jumps to $9.1 Billion: Report

Reko Diq Project Cost Jumps to $9.1 Billion: Report

The Reko Diq project cost has risen 30 per cent to $9.1 billion from an earlier estimate of $7 billion, while first production could be delayed by two years to 2030, according to a report by the Institute of Cost and Management Accountants (ICMA).

The rising price tag and the possible delay increase the financial risk for three Pakistani state-owned enterprises that have committed about $1.88 billion to the mining project in Balochistan.

The figures highlight the growing exposure of Oil and Gas Development Company Limited (OGDCL), Pakistan Petroleum Limited (PPL) and Government Holdings (Private) Limited (GHPL), which together own 25 per cent of Reko Diq. International mining company Barrick holds a 50 per cent stake, while the Government of Balochistan owns the remaining 25 per cent.

Reko Diq project cost rises in both phases

The ICMA report breaks the increase down by phase. Phase I investment is now estimated at $5.6 billion, up from $4 billion, while Phase II costs have climbed to $3.5 billion from $3 billion.

The project is designed around a 37-year mine life and a two-phase development plan. Phase I is expected to process 45 million tonnes of ore a year, with capacity rising to 90 million tonnes under Phase II.

The higher cost matters because the three state firms have already committed large sums. For them, delays could postpone dividend income, increase financing exposure and raise the opportunity cost of committed capital. The report says the rising investment needs make cost controls, transparent monitoring and timely execution increasingly important.

Security concerns add to project delays

The rising costs come as Reko Diq faces development uncertainty after security concerns in Balochistan. Barrick began a review of the project in February 2026 and announced a slowdown in development in April, extending the review until mid-2027 to reassess security conditions, financing, capital requirements and project timelines.

First production, originally targeted for the end of 2028, could now shift to 2030, although Barrick has not formally confirmed a revised production date. The company has also cautioned that previously disclosed project costs and schedules could change, while estimates of extra capital needs remain uncertain.

The delay itself is not new. Dawn reported in early November, citing government and industry sources, that production could slip to 2030 because of security concerns in Balochistan and the war in neighbouring Iran.

Barrick chairman John Thornton was in Islamabad last week for the Pakistan Minerals Investment Forum 2026, where he addressed the forum and met Prime Minister Shehbaz Sharif. Barrick expressed keen interest in investing in mineral processing industries in Karachi and Gwadar, but gave no signal on when the company will commit to a full construction schedule.

The project also faces a transport question at home. The government has already deferred the ML-3 rail project linked to Reko Diq for a third time over funding, as the CDWP deferred the ML-3 project again on 15 November.

What the project could still deliver

Despite the financial risks, the project carries large long-term economic potential. It is estimated to generate about $74 billion in free cash flow over its projected 37-year mine life, with peak construction employment of 7,500 workers and around 4,000 permanent jobs.

That figure needs care. Projected cash flow is not the same as revenue accruing directly to Pakistan. Actual benefits will depend on ownership distributions, taxes, royalties, reinvestment and the participation of domestic businesses in the project.

The development could strengthen mineral exports, generate government revenue and create demand for local engineering, construction, transport and maintenance services.

One gap remains. Reko Diq is currently designed to produce copper and gold concentrate, with smelting and refining outside the project’s existing scope. That means domestic value addition is not guaranteed despite Pakistan’s participation in the venture.

Developing local processing would depend on commercially viable access to energy, infrastructure, technology and markets. Policymakers would also need to monitor local supplier participation, skilled employment, workforce training, government revenues and opportunities for domestic processing.

Reko Diq represents a potential shift in how Pakistan’s state-owned enterprises take part in the economy, moving beyond traditional operations towards strategic equity investments alongside international companies. The ICMA report argues that commercial viability must stay central to such decisions, with transparent disclosure of capital commitments, independent oversight, regular financial and operational assessments and clear shareholder accountability.

The test is now practical: whether the project can hold its revised cost and schedule, or become another financial burden on public enterprises. The answer will shape Balochistan’s mining future and how far Pakistan can press its minerals push, from SIFC-backed cement investment and HUBCO’s aluminium smelter study to the policing of illegal mining that led the Khyber Pakhtunkhwa governor to suspend gold mining leases in Kohat.

Frequently asked questions

How much has the Reko Diq project cost risen by?

The estimated development cost has risen 30 per cent, from $7 billion to $9.1 billion, according to an ICMA report. Phase I rose from $4 billion to $5.6 billion, and Phase II from $3 billion to $3.5 billion.

When will Reko Diq start production?

First production was originally targeted for the end of 2028. It could now shift to 2030, though Barrick has not formally confirmed a revised date.

Who owns Reko Diq?

Barrick holds 50 per cent, the Government of Balochistan holds 25 per cent, and three Pakistani state-owned firms, OGDCL, PPL and GHPL, together hold 25 per cent.

How much have Pakistani state firms committed?

OGDCL, PPL and GHPL have committed about $1.88 billion to the project between them.

What could Reko Diq earn over its life?

The project is estimated to generate about $74 billion in free cash flow over its 37-year mine life. That is cash flow, not revenue directly accruing to Pakistan, which will depend on taxes, royalties and ownership distributions.

Feature Pakistan News Desk
Feature Pakistan News Desk
Feature Pakistan News Desk is the editorial team of Feature Pakistan, an independent digital news platform based in Pakistan. The desk reports national, world, business, sports, technology, health and education news, and every story is cross-checked against multiple sources before it is published. To reach the newsroom — including for corrections — email featurepakistanofficial@gmail.com or use the Contact page at featurepakistan.com/contact-us/.