Islamabad Convention Centre Gets Rs14.6bn Lowest Bid
The Capital Development Authority (CDA) has opened financial bids for a new Islamabad convention centre, with the lowest offer recorded at Rs14.6 billion. Dawn reported the bids on Tuesday.
The CDA opened the bids on Monday for the construction of a new convention centre and the upgradation of Jinnah Convention Centre (JCC) for next year’s Shanghai Cooperation Organisation (SCO) summit.
The SCO summit is likely to be held in August next year in Islamabad. The CDA is going to overhaul the JCC and build a new convention centre of a similar size next to it.
CDA officials said the project will likely be completed in six months. The construction firm will hand over the centre to the civic agency on June 30.
Three bids, one clear lowest
Three joint ventures were in the race for the contract. A joint venture of Habib Construction Service (HCS) and Guarantee Engineers turned out to be the lowest bidder, with a quoted rate of Rs14.6 billion.
The joint venture of Shaanxi Construction Engineering Group Corporation Limited, as lead partner, and Umer Jan and Company quoted Rs17.3 billion. The joint venture of China First Metallurgical Construction Company and Matracon quoted Rs14.8 billion.
“We are sure we will get this project completed in six months time as lowest bidder HCS and its partner are known for completing projects in shortest time. HCS completed several road projects in Islamabad in record time including construction of Kashmir Chowk underpass in just 28 days. So, this JV will complete the project in record time and we will take over new building and JCC from construction firm by June 30 to complete checklists process in checking finishing works. Then after complete satisfaction, building will be handed over to the federal government for SCO,” a CDA officer said.
He said heads of SCO member states will be in Islamabad next year, and the CDA and other departments were working on the direction of the government to make the SCO summit a successful and remarkable event.
Pakistan has stayed engaged with the SCO platform. Musadik Malik represented Pakistan at an SCO forum on climate and heritage this month, which shows the grouping remains an active part of the country’s diplomacy.
Islamabad convention centre and the Rs3bn question
The new centre is not the first time the CDA has spent heavily on the JCC. In 2024, the CDA spent around Rs3 billion on the facelift and overhauling of JCC for the SCO foreign ministers’ meeting. Now the civic agency will spend around Rs3 billion more on the renovation and overhauling of the existing JCC building.
That repeat spending has raised questions inside the civic agency itself.
“Construction of a new convention centre is a good initiative. But, there is an interesting fact. Just two years ago CDA spent Rs3 billion on the JCC and now once again it is planning to spend around Rs3 billion more. There is a need to check if funds were properly utilised last time. If funds were properly utilised then what is the new requirement now. Maybe CDA is right, but there is no harm in checking this aspect as well,” an official source said.
The concern is not abstract. The government’s own corruption risk assessment ranked the CDA third among 25 federal institutions, with a risk score of 49.5, which puts its procurement and spending under a spotlight.
Federal spending is also under Senate scrutiny more broadly. The Senate was told the Centre spent Rs2.6 trillion on devolved ministries over 16 years, a finding that has sharpened questions about how public money is used.
The CDA had earlier planned a much bigger project. It wanted to construct a mega New Islamabad Convention, Exhibition and Expo Centre (NICEEC) near Malpur, and received bids of Rs37 billion. Due to shortage of time, the CDA dropped the plan and opted for the new project instead.
Islamabad’s civic works are moving on other fronts too. The capital’s 130 union councils were finalised this year after delimitation objections were dismissed, which sets the administrative map the CDA works within.
The test for the new centre will be the June 30 handover date. If the lowest bidder meets it, the building will be ready in time for the SCO summit. If it slips, the government will have to explain why a project awarded on speed did not deliver on it.
Frequently asked questions
What is the lowest bid for the new convention centre?
A joint venture of Habib Construction Service and Guarantee Engineers quoted Rs14.6 billion, the lowest of three bids opened by the CDA on Monday.
When will the centre be ready?
CDA officials said the project will likely be completed in six months, with the construction firm handing over the centre to the civic agency on June 30.
Why is the centre being built?
It is being built for next year’s SCO summit, which is likely to be held in August in Islamabad, along with an overhaul of the existing Jinnah Convention Centre.
What were the other two bids?
Shaanxi Construction Engineering Group with Umer Jan and Company quoted Rs17.3 billion, while China First Metallurgical Construction Company with Matracon quoted Rs14.8 billion.
What happened to the earlier expo centre plan?
The CDA had planned a mega New Islamabad Convention, Exhibition and Expo Centre near Malpur with bids of Rs37 billion, but dropped it due to shortage of time and opted for this project instead.